Solar System Permit Guidelines
SOLAR SYSTEM PERMIT GUIDELINES
-Submit a completed Construction Permit Application:
UCC FORMS PRINTED FROM THE INTERNET OR COPIES OF UCC FORMS MUST BE SUBMITTED SIGNED AND SEALED AS REQUIRED.
UCC FORMS MUST LEGIBLE AND NOT HAVE OFFICE ONLY SECTIONS BLACKED OUT
[ ] Construction Permit Application Folder
[ ] Building Subcode Technical Section
[ ] Electric Subcode Technical Section
[ ] Fire Subcode Technical Section
[ ] Zoning Application -Submit payment of $30.00 payable to “Borough of Mendham”
Submit 3 Copies of Layout plan for the Roof Mounted panels
-Submit 2 copies each of manufactures specs and 3 copies of the signed/sealed plans For Solar Photovoltaic Systems: Indicate KW of System, AMP size of Subpanel and any additional components as installed.
-All prior approvals are required to be received prior to permit application being processed. Prior approvals include:
Zoning
Historical Preservation Commission – HPC (if located in the historical zone)
Home Owners Association HOA (If your project is subject to a HOA approval)
After your application is approved by all Subcode Officials, you will receive an email with the amount due. Payment can be made by check, or money order payable to Borough of Mendham.
Rough Electric Inspection is REQUIRED for ALL Solar Projects prior to installation of panels. Inverters, Disconnects, Wiring, Piping, Grounding, Rapid Shut Down, etc. need to be visible.
Questions??? Please contact: Construction Code Official, Rob Rosendale (973) 543-7152 ext 21 Electrical Subcode Official, Chris DeAngelo at cdeangelo@mendhamnj.org Zoning Officer, Neil Schetelick (973) 543-7152 ext 23
***AT THE COMPLETION OF THE JOB, A CERTIFICATE OF APPROVAL IS SENT VIA EMAIL ONLY. INCLUDE AN EMAIL ADDRESS FOR BOTH THE PROPERTY OWNER & CONTRACTOR***