- EXISTING 1 & 2 FAMILY DWELLINGS ONLY
	- Furnace Replacement with no change in fuel type, no relocation, no significant change in ductwork.
		- Submit Construction Permit Application folder completed and signed.
- Submit Mechanical and Electric Subcode Application with chimney verification form completed, signed and sealed by licensed professional.
 
- Furnace Replacement as above, with new installation of air conditioning condenser plus "A" coil.
		- Submit Mechanical and Electric Subcode Application with chimney verification form completed, signed and sealed by licensed professional.
- Submit Zoning Compliance Application for outdoor condenser unit with survey indicating location.
 
-  Furnace Replacement, no change in location, but change in fuel type.
		- Submit Construction Permit Application folder completed and signed.
- Submit Mechanical and Electric Subcode Application with chimney verification form completed, signed and sealed by licensed professional
 
-  Boiler Replacement with no change in fuel type or location.
		- Submit Construction Permit Application folder completed and signed.
- Submit Mechanical and Electric Subcode Application with chimney verification form completed, signed  and sealed by licensed professional.  
			- If replacing backflow preventer, must list under other.
 
 
-  Furnace Replacement and Relocation.
		- Submit Construction Permit Application folder completed and signed.
- Submit Mechanical and Electric Subcode Application with chimney verification form completed, signed  and sealed by licensed professional.
			- If installing a chimney liner
				-  Submit a Mechanical Subcode Application 
					- Indicate a liner under "other" and include a spec sheet for the liner.
 
 
-  Submit a Mechanical Subcode Application 
					
 
- If installing a chimney liner
				
 
 
- Furnace Replacement with no change in fuel type, no relocation, no significant change in ductwork.
		
-   NEW CONSTRUCTION AND ADDITIONS
	- Furnance or Boiler Install
		- Submit Construction Permit Application folder completed and signed
- Signed and Sealed Electric, Plumbing and Fire Subcodes are required.
 
 
- Furnance or Boiler Install
		
 
						 
						 
						 
						 
						 
								 
						 
		    							 
		    							 
		    							 
		    							 
		    							 
		    							 
		    							 
		    							 
		    							 
		    							